HI 110 / 200 / 300 Burner Setup
ghi_tx001449gb.fm 43
Adjusting fuel
pressure
8. Adjust the fuel pressure if necessary using the adjusting screw (e) and re-check
the settings. Repeat steps 4–6 to re-check the settings.
NOTICE: Do not adjust the fuel pressure to a setting outside the safe operational
parameters.
9. Remove the pressure gauge (d) from the pressure test port (c).
10.Re-install the threaded plug (b) into the pressure test port (c).
11.Re-connect the solenoid wire.
12.Close the access panel and re-install the two bolts (a) that secure the panel.
6.7 Setting the Air Band
Requirements
Machine shut down
Power disconnected
Procedure
Perform the procedure below to set the air band.
1. Shut down the machine and allow it to cool.
2. Disconnect the power cord from the power source.
3. Remove the access panel. See topic Removing the Access Panel.
4. Loosen the wing nut (a) and slide the air band (b) as needed. The front edge
should line up with the graduations (markings) on the flame head (c).
5. Tighten the wing nut.
Result
The air band has now been set.